Fit-out Project Progress Milestones

1.

Reviewing of the Start-up package; Fit-out Manual Guidelines, RDD forms

2.

Preparation/Submission of the Concept Design

3.

Preparation/Submission of the Detailed Architectural Drawings, MEP drawings

4.

Obtaining the Landlord NOC

5.

Contractor Appointment letter; to be provided by the tenant

6.

Hoarding Installation / Artwork submission for hoarding /Graphics Installation; if required

7.

Reviewing/Submitting the requirements of the Pre-mobilization documents...

8.

Submitting the Work schedule

9.

Attendance of the site team to the safety induction, requested by the HSE department

10.

Obtaining the Permit to Work from the Landlord

11.

Commencing the site mobilization; Temporary power and water

12.

Applying to authorities such as DM/DDA/DCD/DEWA

13.

Completion of the first fix works; Ceiling closure inspection to be raised

14.

Completion of the second fix works; DEWA inspection to be raised

15.

Completion of DEWA inspection

16.

Installation of DEWA meter; by DEWA; obtaining permanent power

17.

Completion of site works; DCD inspection to be raised

18.

Obtaining the DCD completion certificate: DDA/DM inspection to be raised

19.

Obtaining the DDA/DM completion certificate; Landlord Pre-opening inspection to be raised

20.

Handover of the project/shop to the client/tenant

21.

Obtaining the Landlord Permission to Trade Statement