MIDDLE EAST DESIGN & FIT OUT
Reviewing of the Start-up package; Fit-out Manual Guidelines, RDD forms
Preparation/Submission of the Concept Design
Preparation/Submission of the Detailed Architectural Drawings, MEP drawings
Obtaining the Landlord NOC
Contractor Appointment letter; to be provided by the tenant
Hoarding Installation / Artwork submission for hoarding /Graphics Installation; if required
Reviewing/Submitting the requirements of the Pre-mobilization documents...
Submitting the Work schedule
Attendance of the site team to the safety induction, requested by the HSE department
Obtaining the Permit to Work from the Landlord
Commencing the site mobilization; Temporary power and water
Applying to authorities such as DM/DDA/DCD/DEWA
Completion of the first fix works; Ceiling closure inspection to be raised
Completion of the second fix works; DEWA inspection to be raised
Completion of DEWA inspection
Installation of DEWA meter; by DEWA; obtaining permanent power
Completion of site works; DCD inspection to be raised
Obtaining the DCD completion certificate: DDA/DM inspection to be raised
Obtaining the DDA/DM completion certificate; Landlord Pre-opening inspection to be raised
Handover of the project/shop to the client/tenant
Obtaining the Landlord Permission to Trade Statement